Proposed Federal Correctional Institution and Federal Prison Camp
Letcher County, Kentucky
Project Schedule
Provided below is the current schedule for conducting the environmental impact study process outlined by the National Environmental Policy Act, including opportunities for stakeholders and the public to share comments and provide input. The schedule, subject to change, has been updated periodically over the course of preparing the Draft and Final Environmental Impact Statements and leading to the Record of Decision.
Milestone
Notice of Intent to Prepare Draft EIS
Public Scoping Process
Public Scoping Meeting (Letcher County)
Publication of Draft EIS
Public Review of Draft EIS
Draft EIS Public Meeting (Letcher County)
Draft EIS Public Comment Period Ends
Publication of Final EIS
Public Review of Final EIS
Record of Decision
​
Schedule
September 28, 2022
September 28, 2022 - November 30, 2022
November 17, 2022
March 1, 2024
No less than 45 days following Draft EIS publication
March 28, 2024
April 15, 2024
July 12, 2024
No less than 30 days following Final EIS publication
Signed and Published in the Federal Register on 10/28/2024